Route 100 in Exton Is Getting a Third Northbound Lane. Here's the Timeline.
By Real of Pennsylvania — November 24, 2026
PennDOT plans to add a third northbound lane on Route 100 near the Exton Bypass, along with a new sidewalk to Whiteland Woods. Construction is proposed for 2028 to 2030.
Anyone who drives north on Route 100 through Exton at rush hour knows the squeeze near the Route 30 Bypass, where traffic funnels under the railroad bridges. PennDOT has a project in the works to ease it. The Route 100 Widening Project in West Whiteland Township would add a third northbound lane on Pottstown Pike, running north to the eastbound on-ramp for the Route 30 Exton Bypass. According to PennDOT's project page, last updated in June 2026, construction is proposed to start in June 2028 and finish in April 2030.
The new lane is designed to fit within the road's existing width under the Amtrak and SEPTA bridge and the former Norfolk Southern bridge, so the bridges themselves won't be rebuilt. To make room, the center median will be replaced with a narrower one shifted toward the southbound side, leaving two southbound lanes and three northbound lanes, each 11 feet wide. Concrete barriers and guide rail will protect the bridge supports. The project also adds a sidewalk along the southbound side from the Route 30 eastbound off-ramp to Whiteland Woods Boulevard, connecting to the existing sidewalk in the Whiteland Woods neighborhood.
The project is in the second of its four stages, with final design next. The Chester County Planning Commission's June 2025 list of transportation priorities put its construction cost at about $6.3 million. It is one of several road projects around Exton in the coming years, alongside the planned rebuilding of interchanges on the Route 30 Bypass to the west.
For homeowners and buyers, road work like this cuts both ways. During construction, expect lane shifts and night work near the bypass. Once it is finished, a smoother drive toward Lionville, Eagleview and the Turnpike could make the neighborhoods along Route 100 a little easier to live in. The new sidewalk is a small but real improvement for Whiteland Woods residents who walk toward the shops near the bypass.
We will update this page when PennDOT posts final design plans or a public meeting date. For more on the area, see our West Whiteland Township guide and our Exton guide. If you would like updates like this in your inbox, the Chester County Review newsletter carries them each month.
Common questions
When will the Route 100 widening happen? PennDOT's proposed schedule is June 2028 to April 2030.
Will the railroad bridges be replaced? No. The new lane fits under the existing bridges, and no bridge work is planned.
Is there new sidewalk? Yes, on the southbound side from the Route 30 eastbound off-ramp to Whiteland Woods Boulevard.
Where can I find project updates? PennDOT District 6 posts updates on its Route 100 (Pottstown Pike) Widening Project page, project number MPMS 118025.